PILOT PHASE – CEPP IMPLEMENTATION SCHEDULE
|
|
|
Phase
|
Dates
|
Activity
|
|
| |
|
1
|
April - May 07
|
Curriculum development & consultation
|
|
|
2
|
30th April – 2nd May 07
|
Leaders Envisioning Workshop
|
|
|
3
|
7th May – 12th May 07
|
Empowerment Team Training Workshop
|
|
|
4
|
14th – 18th May 07
|
Ground – breaking seminar by ET
|
|
|
5
|
21st May – 1st June 07
|
Field work by ET with oversight by programme staff
|
|
|
6
|
4th June – 7th June 07
|
Reflection Workshop with the ET
|
|
|
7
|
11th June –3rd Aug 07
|
Field work by ET with oversight by programme staff
|
|
|
8
|
30th July – 3rd Aug 07
|
Field Review & report development by Consultant
|
|
|
9
|
27th Aug - 1st 07
|
Review Workshop with ET, consultants & programme staff – Possible re-design to utilize available resources.
|
|
|
10
|
Report Writing – Consultants
|
|
|
11
|
3rd Sep – 28th Sep 07
|
Scale up proposal development
|
|
|
10
|
October, November, December 07
|
Follow up with monthly meetings at the constituencies
|
|